Accessible Elevator Construction

The Toronto Transit Commission has an ongoing program to improve public accessibility. New information will be posted as it becomes available.

Union Station - Second Platform Project

The Lift at Union Station from street to concourse has been taken out of service as part of the start of construction for the Union Station Second Platform Project. These are the accessible alternatives for Union Station.

Lawrence West Station - Elevator Installation

Regular maintenance of TTC elevators and escalators keeps them working reliably and safely. To complete this important work, specific units will need to be out of service from time to time.

Following is a list of planned maintenance. Please note: Locations and schedules are subject to change without notice.

Elevator icon Elevators - Planned Maintenance

Station Elevator Location Scheduled Start Date Scheduled Completion Date
Queen StationConcourse to Southbound subway platform January 17, 2012February 24, 2012

Escalator icon Escalators - Planned Maintenance

Station Escalator Location Scheduled Start Date Scheduled Completion Date
Pape StationSouth Side - West End - Eastbound Platform To Concourse February 10, 2012February 12, 2012
Sheppard-Yonge StationConcourse To Train Platform December 17, 2011April 26, 2012